[ www.vuZs.net ] one important query must answer


specially BCS , MIT ,MIS, BIT, MCS students,


in project software management system, according to planned scheduling


For how many days, the start of Task (E) can be delayed without affecting the project completion date??



need logical answer with reason..




-- --