[ www.vuZs.net ] one important query must answer


specially BCS , MIT ,MIS, BIT, MCS students,



in project software management system, according to planned scheduling


For how many days, the start of Task (E) can be delayed without affecting the project completion date??



need logical answer with reason..




-- --
Please visit www.vuzs.net For Current & Old Papers, Quizzes, Assignments and study material.
 
To post a new message on this group, send email to vuZs@googlegroups.com
 
Message Posting Rules: http://www.vuzs.net/faq/4795-vuzs-google-groups-basic-rules-for-posting-messages.html
--
To unsubscribe from this group, send email to vuZs+unsubscribe@googlegroups.com
--
To join this group Send blank email to vuZs+subscribe@googlegroups.com
or visit
http://groups.google.com/group/vuZs/subscribe

0 comments:

Post a Comment

 
College & Education © 2012 | Designed by